Concrete slabs and front wall before being taken down.

F
ront view 
400mm taken out the solid subsoil which was London clay

Pegging out for drive height boards which we placed down to enable client to walk on

As this is a residential property, we had to take clients needs into consideration so provided a route for pram

Gulley placed to take water off driveway with silt bucket

Leanmix concrete laid, lots of wet weather, London clay and rain = Glue and mess

Extra work ducting for garden lights

Existing wall removed, new footing and
reclaimed stone used

Wall completed with reclaimed coping stones. Notice curve to coping, done on site

Setting bands to outside area

Bands are laid on 4:1 sharp sand cement

Bands and new walls to front door

Walls to front door and boards for client to walk on. Highly polished original floors in house.

New bullnosed
steps and copings to front door

Start of sett laying on 4:1sand cement. Each sett laid and tapped in with lump hammer

Setts to corner where gulley is

Sett laying going well, laid out behind us for easy selection

Sunny day which means Cookie crew are happy

Instarmac flowpoint in garage, ready for pointing

Nearly at the end of the drive

To the pavement we installed ACO drain with cast iron grids. Water taken under wall to garden into suds crates with overflow into storm drain.


Ready for flowpoint

Pre-wetting before pointing

Flowpoint is set within 20 minutes, as you can see it is a clean finish

Garden makeover done and returned to its former glory